Skip to content

What are the additional costs for the end user if the contractor is deemed employed?

The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.

Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.

Related FAQs

What if a contractor is deemed to be employed?

The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.

If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.

What if the status determination is disputed?

You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.

If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.

Records of disputed determinations and the outcome of any appeal should be kept.

If an employer identifies that higher PPE spec is required for BAME employees undertaking a particular task, is it necessary to increase the spec for all employees working in that area?

It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.

So the short answer is yes.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

How do I determine contractor status?

You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.

Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.

The key factors used to determine status  are:

  • Control:
    • How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
  • Personal service:
    • Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
  • Mutuality of obligation:
    • Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?