What are the additional costs for the end user if the contractor is deemed employed?
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
Related FAQs
The only potential negatives are the potential for MHFAs to become overloaded, or for MHFAs to overstep the boundaries of their role. Both would be avoided if a suitable framework is in place around them, and if adequate ongoing support and training is provided.
As the pandemic progresses, more and more people will be forced to self-isolate and, inevitably, both tenants and staff will be affected. Put plans in place to mitigate the impact that this may have, particularly regarding staff shortages. The most important focus here should be communication.
The Covid-19 outbreak will affect the pace of everyday life and delays will be expected. Rather than allowing the pandemic to take over completely, it is important to maintain open communication with tenants as much as possible and inform them of any front-facing challenges that you may face.
The Protocol does envisage that delays may occur and allows for some degree of flexibility. Whilst all efforts should be made to conduct inspections where practical and possible, it should be expected by all parties that timescales will be extended during this crisis. It is fundamental, however, that all changes made to standard practice are communicated and explained to tenants to manage expectations.
Similar flexibility should be afforded to tenants. As households are required to isolate it will not always be possible to gain access to properties as would usually be expected and required. Likewise, vulnerable people will wish to protect themselves and their families and may refuse access on this basis. During this period, a degree of understanding must be exercised and concessions made.
Inspections may be delayed if anyone in the household has symptoms. A questionnaire should be prepared for those visiting properties to assess so far as possible the risk; Personal Protective Equipment should be issued to those visiting, and government guidelines followed.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.
Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.