What are the consequences of the shake up of the planning Use Class system?

The Town and Country Planning (Use Classes) (Amendment) (England Regulations) 2020 were laid before Parliament and come into force on 1 September 2020. They apply in England only.

The changes include the revocation of the following Use Classes;

  • A1 – shops
  • A2 – financial and professional services
  • A3 – restaurants and cafes
  • A4 – drinking establishments
  • A5 – hot food takeaways
  • B1 – business. Also revoked are the sub parts of B1;
    • B1(a) – offices
    • B1(b) – research and development of products and processes
    • B1(c ) – industrial process
  • D1 – non residential institutions
  • D2 – assembly and leisure

The changes include the amendment of the following Use Class;

  • B2 (industry)

The changes include the introduction of the following Use Classes;

  • E – commercial, business and service
  • F.1 – learning and non-residential institutions
  • F.2 – Local community

There are no changes to the following Use Classes;

  • C1 – hotels, boarding and guest houses
  • C2 – residential institutions
  • C3 – dwellinghouses
  • C4 – small HMO

From 1 September 2020;

  • Small retail shops (not more than 280 sq metres net sales area) selling essential goods including food and at least 1 kilometre from another shop will cease being an A1 use and will become a F.2 (local community) use;
  • Other A1 shops will become an E (commercial, business and service) use;
  • A2 uses will become an E (commercial, business and service) use;
  • A3 uses will become an E (commercial, business and service) use;
  • A4 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
  • A5 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
  • B1 uses (included B1(a), B1 (b) and B1 (c) will become an E (commercial, business and service) use;
  • B2 uses will either be B2 uses or will be Class E uses.
  • Clinics, health centres, creches, day nurseries and day centres (previously D1 uses) will become an E (commercial, business and service) use;
  • Schools, non residential education and training centres, museums, public libraries, public halls, exhibition halls, places of worship, law courts (previously D1 uses) will become an F.1 ( learning and non-residential institutions) use;
  • Cinemas, concert halls, live music performance venues, bingo halls and dance halls (previously D2 uses) and will be sui generis, ie not in any use class;
  • Gyms, indoor sport, recreation or fitness not involving motorised vehicles or firearms principally to visiting members of the public (previously D2 uses) will become an E (commercial, business and service) use;
  • Hall or meeting place for the principal use of the local community (previously D2 uses) will become an F.2 (local community) use;
  • Indoor or outdoor swimming baths, skating rinks, outdoor sports or recreation grounds (not involving motorised vehicles or firearms) (previously D2 uses) will become an F.2 (local community) use.

Changes of use within a Use Class do not constitute development. That being the case, provided the Order is applicable, its operation not having been restricted by planning condition, Agreement or Article 4 (1) Direction for example, planning permission would not be required, development as defined not happening.  If legally binding confirmation is required that planning permission is not required this can only be obtained by way of a successful application for a Certificate of Lawfulness. In the absence of such, there is some risk.

It remains the case that planning permission may be required for operational works to buildings. It also remains the case that other consents and permissions may be necessary for example licenses. Furthermore amendments to leases may be required if the property is rented.

The Regulations additionally include transitional arrangements because of permitted development rights for changes of use in the Town and Country Planning (General Permitted Development) (England) Order amongst others.  To respond to this Regulations introduce a ‘material period’ which is defined as meaning the period beginning 1 September 2020 and ending 31 July 2021. It is expected during the material period the Orders giving permitted development rights for changes for use which do constitute development will be amended / updated to reflect the new use classes.

Click here to view the Regulations.

The above is based on our understanding of the new Regulations at the time of issue and in advance of planning practice guidance being issued.

Related FAQs

What is the Clinical Negligence Scheme for Coronavirus?

The Government has recently passed the Coronavirus Act 2020 in a response to the challenges posed by the pandemic, especially in relation to those facing the NHS during this time of crisis.  NHS Resolution worked closely with the Department for Health and Social Care to draft a clause within the Coronavirus Act providing indemnity for clinical negligence for any coronavirus related activity not currently covered by an existing arrangement.  In order to implement this clause, NHS Resolution has launched the Clinical Negligence Scheme for Coronavirus (“CNSC”).

It is intended that the CNSC will cover new contracts put in place for healthcare arrangements to respond to coronavirus, such as organisations supporting testing arrangements or Independent Contractors making agreements with NHS England and NHS Improvement to release capacity to the NHS.  Membership is not required for this scheme and the contracts entered into will automatically provide indemnity under the scheme.

The CNSC will not replace existing indemnity provisions made under the Clinical Negligence Scheme for Trusts (“CNST”) and it has been confirmed that the new Nightingale Hospitals will be covered by CNST rather than CNSC.  Similarly, NHS Resolution have confirmed that those doctors and nurses returning to practice from retirement, or those joining as students will be covered by the CNST or, where applicable the Clinical Negligence Scheme for General Practice (“CNSGP”).  The CNSC will not cover returning midwives to the profession, but the Royal College of Midwives have confirmed that they will extend all of the benefits of membership including Medical Malpractice Insurance to returning retired midwives.

For more information regarding this please click here.

What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.

Do you think MHFA will become a legal requirement for businesses eventually?

This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.

Forcing annual leave

Employers have a statutory right to require employees to take annual leave at their direction, subject to providing staff with notice equal to at least double the length of the leave that you are directing them to take (e.g. 10 days’ notice for five days leave). However, this measure is not likely to achieve any urgent cost savings or alleviate immediate cash-flow pressure as holidays would need to be paid.

Clearly, annual leave can be taken on furlough so you could have staff on furlough and annual leave.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.