What challenges to planning permission does the current lockdown situation present?
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
Related FAQs
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
The Government assured parity for the self-employed but it has since accepted that this would be difficult to achieve. The Association of Independent Professionals and the Self-Employed (IPSE) has worked closely with the Government on implementing the current self-employment income support scheme. IPSE has confirmed that it will continue to work on helping to extend measures to all freelancers in need as a result of Covid-19.
The Government announced an extension to the Self-Employment Income Support Scheme from 1 November 2020.
Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.
A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.
Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.
New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.
It is clear that we are emerging from a completely unprecedented period of disruption for many businesses, and this may have had a huge impact on their contractual arrangements both with suppliers and customers.
As the lockdown eases, and we get back to business, it’s important that businesses take stock of what has happened, and ensure they review and address the legal and contractual consequences of what has been happening since the start of the global pandemic.