What do we do if we cannot meet the Court directions order / timetable?
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Related FAQs
The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.
When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).
The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.
As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.
Sections of the video and their timings are as follows:
(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)
(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II
(05.36) – bounce back loans have been a distraction
(06.27) – muted impact of fintech CBILS lenders
(07.52) – discussion about invoice discounting
(11.59) – looming insolvency environment
(12:52) – emerging themes
The basics of health and safety law requires that employers take “all reasonably practicable steps” to ensure workers’ safety and that a suitable and sufficient assessment of risk is undertaken. It is the individual assessment of Covid-19 risk in each workplace that will be central. Employers will be required to conduct a robust risk assessment and then, following the hierarchy of controls, put robust processes and safeguards in place to address those risks.
UK government guidance and HSE advice is continually evolving, which in practice means that any risk assessment will need to be reviewed very regularly as that guidance develops. There is flexibility for individual businesses within the overall government framework and there will need to be a process of evaluation to ensure that the measures in place continue to meet the requirements.
The starting point of avoid, eliminate and control means looking at individuals continuing to work from home where possible (the fewer the number of people back in the workplace the lower the risk), and if not look at risk management, which leads to administrative controls – i.e. changing work practices before ending up at PPE. PPE is generally seen as control of last resort but in practice – facemasks, disposable gloves and constant prompts to wash hands for example.
In terms of changing working practices, employers should be thinking about:
- the workspace and how this is laid layout
- how do we make sure it is kept clean and hygienic
- how do we keep people apart
- how can we use toilets, canteens or other shared spaces/facilities safely
- how do we promote and enable higher levels of workplace hygiene
- if we are going to rely on PPE – can we get it, and is it suitable
- what about limiting customer interactions
- will there be enough first aiders on site
- can we manage fire safety, deliveries etc
- what about higher risk workers
- should work tools and equipment be allocated on an individual basis to employees.
These decisions need to be recorded and clearly communicated to staff members.