What do we do if we cannot meet the Court directions order / timetable?
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Related FAQs
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
The application has to be made before the date on which the accounts should have been filed, so this process can’t be used if you are already late. If you don’t make the application before your filing deadline, then a fine will automatically be generated if your accounts are filed late. Whilst you could appeal against such a fine on the grounds that the delay was caused by coronavirus issues, this is likely to be a much more time consuming and uncertain process that applying in advance.
It does not appear that the process applies to Confirmation Statements or other returns.
The Commission has provided guidance as to measures which Member States can introduce without notification. These include:
- Measures which apply to all businesses within a Member State (for example the furloughing measures introduced by the UK Government)
- Measures providing support direct to consumers
- Measures which are already exempt from the notification requirement (discussed further below).
To respond to the crisis the European Commission has also issued a temporary framework to provide a basis for emergency aid to be notified for approval. The framework is initially in place until 31 December 2020. The Commission continues to keep this under review and has twice widened its scope to allow more types of aid to be notified. The type of measures covered include:
- The provision of guarantees (including guarantees for 100% of loans)
- The provision of loans at low interest rates, at zero interest rates or subordinated to senior debt
- Measures to support liquidity needs or to alleviate difficulties caused by the current crisis
- Measures to recapitalise businesses
- Measures to assist sectors hit particularly hard by the current crisis (eg transport)
- Measures targeted at COVID-19 such as research and development or production of products related to tackling the virus
The Commission has approved a UK Government “umbrella” notification to allow UK public authorities to adopt the measures permitted by the Commission framework. Therefore public authorities in the UK can use the Framework without notifying individual measures or schemes to the Commission.
No. You should always treat employees consistently and fairly, but this doesn’t mean treating them all the same, or applying the same requirements. For those employees who have been homeworking and doing so without any problems, then they should be allowed to continue to do so.
We would anticipate that the vast majority, if not all, businesses will be approaching the return on a phased basis, which inevitably means some employees returning to work sooner than others. In reality then, you aren’t treating everyone the same, but try to be fair and consistent; you need to do what works best from a business perspective, but can you rotate people, require them to come in at different times etc. Where people perceive that the planned return is being worked out fairly they are far more likely to buy into this, which will help avoid resentments building up between colleagues.
The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.
When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).
The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.