What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Related FAQs

How do I access the scheme?

Those who are eligible will be contacted directly by HMRC based on tax returns they have received. If you are eligible you will be asked to fill out an online application. HMRC will pay applicants directly.

Are there specific examples given?

The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:

  • Varying deadlines (e.g. for performance or payment)
  • Varying compensation (e.g. to recognise increased costs)
  • Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)

The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.

What if you want to terminate the contract completely?

If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:

  • Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
  • A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all

If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.

Even if the right to terminate the contract does exist, there might be particular rules about the following:

  • How much notice has to be given
  • How such notice has to be served (for example, it might have to be in writing to a particular address)
  • When the notice can be served (perhaps on an anniversary of the start of the contract)
  • How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)

All of these factors must be taken into account, and any contractual processes for termination are followed.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What other factors may be considered?
  • Integration:
    • Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
  • Exclusivity:
    • Is the contractor restricted from working for other organisations without the consent of the end user client?
  • Length of engagement:
    • Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
  • Pay:
    • Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
  • Facilities:
    • Does the contractor provide their own equipment and materials to provide the services?
  • Financial risk:
    • Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?