What do we do if we cannot meet the Court directions order / timetable?
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Related FAQs
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
No one factor will determine status and the outcomes will differ depending on the nature of the work being carried out and the business of the end user client.
When you have carried out an assessment based on the relevant factors you can either get in touch with us to discuss further, check your answers against HMRC’s CEST tool or do both before making a final determination.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
The Cabinet Office has published a helpful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). This can include making advance payments to suppliers, if necessary. The PPN sets out actions that public sector bodies should take (until at least 30 June 2020) to ensure continuity of service and to ensure that its suppliers can resume normal contract activity once able to.
The actions public sector bodies should be taking include:
- Informing its suppliers (that they believe are at risk) that they will continue to be paid as normal until the end of June 2020 (even if service delivery is currently interrupted). Risk might include supply chains collapsing and/or significant financial implications for a supplier
- If a contract involves a payment by results mechanism, basing payments on previous months (e.g. the average monthly payment over the previous 3 months), and
- Ensuring that invoices submitted by suppliers are paid immediately to maintain cash flow in the supply chain and help to protect jobs.
If you are a supplier to a public sector body, you must act transparently and on an open-book basis, making cost data available to your public sector clients. You must also continue to pay your employees and subcontractors / suppliers. Suppliers to the public sector must not expect to make profits on any undelivered elements of a contract. The PPN makes clear that, should suppliers be found to be taking undue advantage, or failing to act transparently, a public sector body can take action to recover payments made to that supplier.
The PPN requires public sector bodies to urgently review their contract portfolios and take steps to support suppliers who they believe are “at risk”. However, no definition of “at risk” is given in the document. We would suggest that if you are a supplier and you have yet to hear from a public sector client, you should seek to get in touch with them as soon as possible, particularly if you have concerns about your supply chain, staff retention and/or are experiencing financial difficulties currently. Given the requirement for transparency, you may be required to provide evidence, so it may be helpful to have any relevant documentation ready to send, if necessary, as this may help ensure a decision is made by the public sector client more promptly, particularly as the public sector body may have a number of contracts to consider.
Yes. Their contracts can be renewed or extended during the furlough period without breaking the terms of the scheme.
If the employee’s contract has not already expired, the contract can be extended or renewed. The employee may be furloughed provided that they were employed on or before 30 October 2020. You must also have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.
If the employee’s contract expired on or after 23 September 2020, the employee can be re-employed and furloughed. Please note that the employee must have been employed by you on 23 September 2020 and you must have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.