What do we do if we cannot meet the Court directions order / timetable?
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Related FAQs
A number of our clients and networks raised issues in the early stages of the Scheme around the requirement for personal guarantees to access finance under the Scheme. The Scheme has now been updated so that:
- For facilities under £250,000, personal guarantees cannot be taken to support lending under the Scheme.
- For facilities above £250,000, personal guarantees may still be required by a lender but the amount which can be recovered under these guarantees is capped at a maximum of 20% of the outstanding balance of the CBILS facility after taking into account any other recoveries from business assets.
The fundamentals of risk assessment remain the same as for any other foreseeable risk.
Focus on risk controls which reflect Government guidance; social distancing (2 metres) and avoiding contact with occupiers if possible, high-quality PPE – disposable overalls, gloves and fluid repellent surgical face masks, ready access to antibacterial wipes for surfaces, tools and equipment and plentiful hand sanitizer.
The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:
- Varying deadlines (e.g. for performance or payment)
- Varying compensation (e.g. to recognise increased costs)
- Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)
The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.
If there is a court order then this should be complied with, unless you are unable to do so because the parent with whom the child lives is self-isolating, the other parent is self-isolating or the children are showing symptoms of the virus. If you are unable to comply with the court order, the other parent should be notified immediately in writing and proposals put forward for how they can see and speak to their children by telephone, FaceTime, Zoom or some other method.
If any necessary variations to the arrangements cannot be agreed then you should contact us for legal advice.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?