What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Related FAQs

Do employers still have to enrol and reenrol employees?
  • Yes, and this includes furloughed employees under the Coronavirus Job Retention Scheme.
  • Employers must continue to assess their new employees or newly eligible existing employees and enrol them where required, but can make use of the statutory postponement procedure which allows them to delay for up to three months the assessment of new employees for the purpose of enrolment (see further details here on the Pensions Regulator’s website). Declarations of compliance for new employers must still be completed in the normal way.
  • Postponement cannot be used for re-enrolment. The Regulator recommends employers use the re-enrolment date tool on the Regulator’s website to choose a date up to three months after the third anniversary of enrolment to assess staff for re-enrolment. Further information about employers’ obligations about reenrolment from the Pensions Regulator can be found here. Re-declarations of compliance for new employers must still be completed in the normal way.
How do EWS1 form requirements apply to leasehold flats sold to secure tenants exercising their Right to Buy under the Housing Act 1985 whether in low, medium or high rise blocks?

Where a lender requires a EWS1 as part of the mortgage requirements for a flat this will apply regardless of its tenure and will therefore apply to applicable RTB properties. It may also be required in order to obtain a valuation for the disposal notices and issues in obtaining it could cause problems in serving this within relevant deadlines required by legislation.

Should we stop employees working from home?

No, government advice remains that if employees can work from home, they should continue to do so in order to minimise social contact across the country in order to keep infection rates down.

What does the guidance suggest?

The guidance asks parties to act responsibly and fairly in performing and enforcing contracts. They are encouraged to act in a spirit of cooperation to achieve practical, just and equitable outcomes. In essence, rather than sticking strictly to the contract as agreed, they are encouraged to give each other leeway to deliver performance differently than they are required to do under the contract.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.