Skip to content

What does the guidance suggest?

The guidance asks parties to act responsibly and fairly in performing and enforcing contracts. They are encouraged to act in a spirit of cooperation to achieve practical, just and equitable outcomes. In essence, rather than sticking strictly to the contract as agreed, they are encouraged to give each other leeway to deliver performance differently than they are required to do under the contract.

Related FAQs

What happens if I need to sign a new commercial lease in the future?

The outbreak is certainly going to have an impact on new lease negotiations.

Undoubtedly many transactions will be put on hold or indeed stop entirely. Where matters are ongoing, tenants may well look to strengthen rent suspension provision.

It is also possible that tenants and their representatives will also now seek to include termination rights for unseen events. In this regard, the concept of force majeure may start to appear more often in leases.

In both of the examples above, such attempts are not likely to be well received from landlords who will undoubtedly suggest that tenants ensure that their business interruption insurance policies are robust enough to protect the tenant in the event of any future pandemic events.

Another approach tenants might adopt going forwards in negotiations for a new lease (or indeed seeking to vary existing leases), is to move away from the traditional market rent model to a turnover rent arrangement. This will offer some protection going forward if trading conditions deteriorate, but again getting institutional landlords to agree such an approach may prove difficult.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

Do I have to continue to pay furloughed staff while furloughed? Can I wait until I receive the money from the government?

To qualify for a grant under the scheme you must pay your furloughed staff the wages you are claiming for. Failure to do so may result in a HMRC investigation and/or claims from furloughed staff for unlawful deductions from wages and possibly constructive dismissal claims.

Normal benefits including non-monetary benefits should continue during furlough unless the individual has agreed in writing to reduce or remove a benefit during this time.

Employers are expected to apply for one or more of the financial support schemes available to be able to continue to pay staff.

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.