What does the new Chief Coroner guidance cover?
This guidance from the Chief Coroner applies to reports of death and coroner investigations in England and Wales. It is to assist coroners in continuing to exercise their judicial decisions independently, in accordance with the law, and during the extraordinarily pressured events being faced at present.
Related FAQs
On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.
To qualify for a grant under the scheme you must pay your furloughed staff the wages you are claiming for. Failure to do so may result in a HMRC investigation and/or claims from furloughed staff for unlawful deductions from wages and possibly constructive dismissal claims.
Normal benefits including non-monetary benefits should continue during furlough unless the individual has agreed in writing to reduce or remove a benefit during this time.
Employers are expected to apply for one or more of the financial support schemes available to be able to continue to pay staff.
As we all adjust and adapt in line with the Government’s guidance throughout this uncertain time, we must consider how we can revise current processes and implement new ones to maintain effective and compliant ways of working. We have identified several key issues that all housing providers should consider.
Protocol Compliance
Housing providers will continue to receive new disrepair claims. Throughout the disruption caused by coronavirus, landlords will still be expected to respond to these claims and comply with the Pre-Action Protocol for Housing Conditions Claims whilst doing so. We address the issue of disclosure in particular below.
Letters of claim will continue to be sent by post to your Registered Office, and the deadlines will run from the date of deemed service. Ensure you have systems to enable you to scan correspondence and forward it to the responsible officer who will handle the claim so deadlines are met.
Under the Protocol, the deadline for disclosure is 20 working days from deemed service of a letter of claim (2 working days after it is sent). So, for example, a letter dated 2 March 2020 would be deemed served on 4 March 2020 and disclosure would therefore be due by 1 April 2020. All housing providers must continue to comply with the Protocol and so landlords should begin preparing now.
Failure to meet deadlines often result in the issuing of further applications to court by tenant’s solicitors which in turn will lead to unnecessary costs orders against landlords.
Therefore, all records, particularly relating to customer contact and repair logs, should be held electronically. If required, this will allow for such documentation to be redacted for GDPR purposes remotely and disclosed to the tenant’s solicitor simply and efficiently.
Remember it is possible to request an extension to all Protocol deadlines and it is inevitable in these unusual times, this will need to be utilised, and should not be refused. Request extensions to deadlines at the earliest opportunity to enable an achievable timescale. It would be a difficult lawyer that would not agree to such a request.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
- Working with PFI providers to get contingency plans up to date
- If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
- maintain unitary charge payments
- revise contract requirements/standards
moderating payment and performance regimes where appropriate.
- In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
- When putting local bespoke arrangements into place it is vital that:
- Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
- It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.