What guidance has the Charity Commission provided?
The Charity commission has issued the following guidance
https://www.gov.uk/guidance/coronavirus-covid-19-guidance-for-the-charity-sector
Related FAQs
The Government has announced a £750 million funding package for charities to ensure they can continue their vital work during the coronavirus outbreak. This is for a 3 month period and further specific funding may be made available.
Charities which are businesses can also access the Government’s Coronavirus Business Interruption Loan Scheme (CBILS) – Please see our Funding and Finance FAQ’s.
Has there ever been a more important time for all staff to feel that they are able to raise concerns about their working environment?
It is a pertinent time to remind all staff that they should be able to raise concerns without the fear of repercussions. It is a good time to be reviewing and re-issuing your Freedom to Speak up/Whistleblowing policy to all. Likewise it is a good time to remind all staff that they should not treat others unfairly or detrimentally for raising health and safety concerns.
Both subjecting someone to a detriment because they have blown the whistle or raised health and safety concerns (and dismissing someone for the same) is unlawful.
We don’t recommend this. Status determination statements must be issued before 6 April 2021 for current engagements and the appropriate deductions are to be made on payments for services carried out on or after 6 April 2021.
The CLC has also prepared a template letter that firms may adopt and issue to their workforce regarding travel to work. This can be accessed at download document.
The CLC’s current advice to those carrying out works on site is to carry out your own risk assessment on each site and determine whether or not it is safe to continue to work in accordance with the Public Health England instructions and the CLC Site Operating Procedures. If it is not possible to work in accordance with the above they should not work.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.