What are the changes to the law?
On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process. This has very important consequences for many businesses as it could expose them to greater financial risks.
Related FAQs
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
Although an employer is obliged to conduct consultation “with a view to reaching an agreement”, it is not required to actually agree to any counter proposals made by the employee representatives. Merely to consider them in good faith.
We have developed a Toolkit to help with these issues. The Toolkit contains:
- LO1 How to Guide: Lay off and short time working
- LO2 Letter directing employee to take annual leave
- LO3 Letter confirming lay off (contractual right)
- LO4 Letter confirming short time working (contractual right)
- LO5 Letter proposing lay off (no contractual right)
- LO6 Letter proposing short time working (no contractual right)
- LO7 Counter notice disputing entitlement to claim redundancy payment
- LO8 Script for announcing lay off or short time working (contractual right)
- LO9 Script for announcing lay off or short time working (no contractual right)
- LO10 Letter proposing reduction in working hours and pay
The cost of this Toolkit is £500 plus vat. If you would like to find out more about the Toolkit, please speak to your usual Ward Hadaway employment contact, or get in touch one of the contacts at the bottom of this page.
Follow up to date UK Government advice. This can be found at: https://www.gov.uk/government/publications/guidance-to-employers-and-businesses-about-covid-19/guidance-for-employers-and-businesses-on-coronavirus-covid-19
For best practice and more detailed information; consult the HSE’s website at https://www.hse.gov.uk/news/coronavirus.htm
Failing to follow the guidance is likely to be regarded as failing to take all reasonably practicable steps.