Skip to content

What if I get the status wrong?

As long as you can demonstrate that you have exercised reasonable care in determining status you have discharged your obligations in that respect. However, if you are unable to demonstrate this, you may as the end user client be responsible for the contractor’s tax and NIC’s.

Related FAQs

VIDEO: In conversation with cashflow.co.uk expert Chris Silverwood about CBILS

Partner at Ward Hadaway Adrian Ballam talks to corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) to explore the practical ins, outs, dos and don’ts of CBILS applications, answering the questions:

  1. How are banks making their assessments of whether a business can afford a CBILS loan when for many they cannot accurately forecast their revenues for at least the next three months?
  2. What are the red flags that banks are looking for when assessing whether or not to grant a request for a CBILS loan?
  3. What cost mitigation measures should a business have already implemented prior to applying for a CBILS loan?
  4. What level of information should a business provide to support a CBILS application?
  5. What common mistakes are businesses making when applying for funding?
  6. What general tips do you have for businesses seeking CBILS funding?

Click read more to view the video.

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
What if the status determination is disputed?

You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.

If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.

Records of disputed determinations and the outcome of any appeal should be kept.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

If a member of staff does not inform me that they ought to be self-isolating will I still be liable for a fine?

Potentially no.

If an employer is not put on notice that the circumstances of a worker or agency worker are such that they ought to be self-isolating, by either the worker or agency worker themselves or another member of staff, then there ought to be a reasonable excuse, and potentially, no fixed penalty notice will be issued.