Skip to content

What if I was promised something which isn’t contained in the Will?

If the testator promised you something during their lifetime which they said that you would inherit on their death, but then this was not provided for in their Will, you may be able to bring a claim known in legal terms as either proprietary estoppel or promissory estoppel.

You must be able to show that the testator made you a promise during their lifetime, that you relied on that particular promise and the reliance that you placed on the promise was to your detriment.   You can find more details above in the FAQ – How long do I have to contest the validity of a Will?

Related FAQs

What type of matters are the Courts still dealing with?

Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:

Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).

Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.

The full guidance can be found at:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/881019/Civil_court_listing_priorities_24_April_2020.pdf

Does this apply to bankruptcy petitions?

No. This bill relates to corporate insolvencies only. Should you require any advice as to personal insolvency situations, please contact our team.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What are the special considerations for DB schemes?
  • Before any agreed reduction in wages, actual changes to earning patterns (loss of overtime, for example) may impact the pensionable salary as defined under the scheme rules, with knock-on effects to a number of benefit calculations, such as death in service benefits.
  • Contractual changes to member salaries may adversely impact accrued benefits as the final salary figure may be reduced to a greater or lesser extent depending on the duration of furlough and the severity of any reductions in wage, and hence reductions may be difficult to agree with staff.
  • Reducing employer contributions will be subject to a number of the same considerations applicable to a DC scheme listed above. There will also be a need to change the rules and interact with the trustees, although it may be possible to override the rules with a direct contractual agreement with members.
  • Reducing employee contributions will also depend on the scheme rules, particularly as to whether there are any discretionary powers to suspend contributions, or pensionable service.
  • The rules will need to be considered for any unexpected consequences of furlough: depending on the wording of the rules, furlough may or may not be considered a leave of absence and may or may not have the effect of terminating pensionable service. This could have far-reaching consequences.
  • In particular, if the workforce’s pensionable service is inadvertently terminated as opposed to suspended in accordance with any relevant rule, this could trigger a statutory employer debt on an employer participating in a multi-employer scheme, if pensionable service continues for employees of other employers. This sort of issue is unlikely to be spotted until after the event, and therefore difficult to untangle. However, an employer should be able to take advantage of the “period of grace” provisions by notifying the trustees of its intention to re-admit employees to pensionable service within the next 12 months.
  • Clearly the impact of the Coronavirus Job Retention Scheme on DB schemes is complex and legal advice should be sought before any changes are considered.