Skip to content

What if the status determination is disputed?

You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.

If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.

Records of disputed determinations and the outcome of any appeal should be kept.

Related FAQs

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

What should I do if I have a hearing scheduled in the COP?

Parties are encouraged to review upcoming matters to assess the viability for there to be any agreement which can be reached in relation to the issues in dispute or to consider whether the case needs to proceed to a remote hearing. If directions or issues can be agreed between the parties, reducing the need for remote hearings, then that is the preferred option.

Do you need to use HMRC's CEST tool?

CEST stands for Check Employment Status for Tax and, although this should do exactly what is says on the tin, there has been criticism of its accuracy and effectiveness. The CEST tool does not test whether there is ‘mutuality of obligation’ in the relationship which is a key factor in determining status.

You are not obliged to use CEST if you are happy with your own assessment process. If you do use CEST keep a record of the certificate given at the end of the assessment and keep this on the contractor’s file. HMRC will stand by the outcome of a CEST assessment provided the information has been honest and accurate. However, you must have entered information honestly to rely on it – you can’t just say what you want to get the right answer, as HMRC may test what you have said.  Also, many people are unhappy with the CEST tool and consider it leans too much towards employed status.

Capability issues

All organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.

Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.

Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.

Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.

As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.

What happens if a patient is admitted to hospital during the pandemic?