What impact does the Regulations have in respect of matters which arise from Fire Safety Audits – e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?
Related FAQs
Specialist healthcare lawyers from Ward Hadaway ran a free webinar looking at the practical and legal considerations if required to treat healthcare workers from a BAME background or other vulnerable groups differently in the fight against the Covid-19 pandemic.
Yes probably in our opinion, even if you are not considering taking any formal action against them. Ultimately if a doctor is suspended this could be considered as causing them reputational damage and it therefore is correct that they are afforded the protections (in particular in relation to keeping exclusion/suspension under review) of MHPS. Under Part V of MHPS there is provision for excluding practitioners if they are a danger to patients and they refuse to recognise it or if they refuse to co-operate. It doesn’t refer to a particular risk for the practitioner themselves, but it would appear logical that it would apply.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.
Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.
Crucially the phrase “force majeure” has no specific meaning in English law. As a result, there is scope for complex legal argument, including as to whether the effects of the coronavirus outbreak can amount to force majeure in the first place. If the coronavirus crisis deepens, force majeure provisions could become relevant in the following ways:
- suppliers to your business might seek to invoke force majeure
- you may need to invoke force majeure under your own contracts
Each of these will need careful analysis of the relevant contract against the applicable factual background. Unfortunately, the position is unlikely to be clear cut.