Skip to content

What impact does the Regulations have in respect of matters which arise from Fire Safety Audits – e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?

The duty would fall on the owner of the building to control the hazards presented by balconies made from combustible materials. There may be scope (via warranties/indemnities or other terms) arising from the contract between the developer and owner for the owner to seek to recover the cost of remedial works.

Related FAQs

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

What will be the added cost to business of furloughing staff from 1 July 2021?

Similar to the position for claims between 1 August 2020 and 31 October 2020, for claims between 1 July 2021 and 30 September 2021 there will be a cost to businesses of furloughing staff, which will gradually increase until the scheme closes at the end of September as follows.

  • From 1 July 2021 employers will be required to contribute 10% of wages, with the Government contributing 70%.
  • From 1 August 2021, the employer contribution increases to 20% and the Government will contribute 60%.
  • 30 September 2021: scheme closes.

Employees will continue to receive 80% of their current wages, up to £2,500 a month.

 

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What is the "Job Retention Bonus"?

As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.

What form does the relaxation take?

The European Commission has reintroduced its “comfort letter” system for cooperation in relation to shortage of supply. This allows cooperating businesses to check what the Commission’s view of their proposals are before implementing them.

In the UK context the SMA has introduced an exemption for suppliers of healthcare services to the NHS. This allows:

  • Sharing information about capacity
  • Coordination of staff deployment
  • Joint purchasing of goods, services and facilities
  • Sharing or lending of facilities
  • Division of activities, including agreeing whether to expand or reduce the volume or type of services provided by suppliers

In relation to whether the CMA will investigate cooperation, it has indicated:

  • The CMA will use its discretion as to the prioritisation of its enforcement action to permit some agreements/collaboration which would otherwise potentially give rise to enforcement action (including potentially attracting fines of up to 10% of group worldwide turnover)
  • The CMA will use its existing power to exempt certain agreements under the Competition Act 1998 where these are in the public interest