What will be the added cost to business of furloughing staff from 1 July 2021?
Similar to the position for claims between 1 August 2020 and 31 October 2020, for claims between 1 July 2021 and 30 September 2021 there will be a cost to businesses of furloughing staff, which will gradually increase until the scheme closes at the end of September as follows.
- From 1 July 2021 employers will be required to contribute 10% of wages, with the Government contributing 70%.
- From 1 August 2021, the employer contribution increases to 20% and the Government will contribute 60%.
- 30 September 2021: scheme closes.
Employees will continue to receive 80% of their current wages, up to £2,500 a month.
Related FAQs
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
It is clear that we are emerging from a completely unprecedented period of disruption for many businesses, and this may have had a huge impact on their contractual arrangements both with suppliers and customers.
As the lockdown eases, and we get back to business, it’s important that businesses take stock of what has happened, and ensure they review and address the legal and contractual consequences of what has been happening since the start of the global pandemic.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Ordinarily, no but during the pandemic, yes.
You can start employing a Tier 2 or 5 worker who is in the UK before their visa application has been decided if the following conditions have been met.
- You have assigned the worker a Certificate of Sponsorship
- They have made an in time visa application (i.e. they made their new visa application before their current leave expired) and they have provided you with evidence of this
- The job you employ them in is the same as the one stated on their Certificate of Sponsorship.
Sponsors should be aware that they should carry out right to work checks before the individual starts undertaking work for them and if their visa application is eventually rejected, they must stop employing them.
Although sponsors will not be able to record migrant activity on the SMS about these workers, the Home Office has confirmed that any necessary reports should still be made on the sponsor’s internal systems.
If the worker is outside the UK, they may be able to start work for you remotely subject to the relevant employment, tax and immigration requirements in that country.