What is the claim period for Flexible Furlough?
Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.
From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.
You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.
For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.
The crucial point is that you cannot make claims that cross calendar months.
The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.
Related FAQs
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Although these measures fall short of the level of assurance given to employees both in terms of eligibility for an immediacy of access to payments, they are a vast improvement on the support for self-employed workers that has been put in place until now. Current support includes:
- Access to business interruption loans
- Self-assessment tax payments that were due in July 2020 have been deferred until January 2021
- VAT is deferred until the next quarter
- The introduction of Time to Pay arrangements under which deferrals for HMRC payments can be agreed
- The minimum income floor for universal credit has been suspended which will allow self-employed workers to access the equivalent of Statutory Sick Pay (SSP)
- Universal credit and tax credit payments to increase by £1000 per year
The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.
PPN 01/20: Responding to COVID-19
The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.
This PPN provides guidance for the following circumstances:
- Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
- Direct award due to an absence of competition or protection of exclusive rights
- Call off from an existing framework agreement or dynamic purchasing system
- Call for competition using a standard procedure with accelerated timescales
- Extending or modifying a contract during its term
PPN 02/20: Supplier relief due to COVID-19
PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.
This PPN provides guidance for the following circumstances:
- Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
- Put in place appropriate payment measure to support supplier cash flow
- Where contract payments are based on ‘payment by results’ make payments based on previous invoices
- Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
- Ensure invoices submitted by suppliers are paid immediately on receipt
PPN 03/20: Use of Procurement Cards
The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.
This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:
- Increase a single transaction limit to £20,000 for key card holders
- Raise monthly limits on spending with procurement cards to £100,000 for key card holders
- Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs
Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.
The PPN also advises that by 30 April 2020, in scope organisations should:
- Ensure that a number of appropriate staff have the authority to use these cards
- Open all relevant categories of spend to enable these cards to be used more widely
Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.
New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.
You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.
Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.
The key factors used to determine status are:
- Control:
- How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
- Personal service:
- Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
- Mutuality of obligation:
- Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?