What is the claim period for Flexible Furlough?
Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.
From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.
You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.
For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.
The crucial point is that you cannot make claims that cross calendar months.
The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.
Related FAQs
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.
When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).
The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.
On 30th April 2020, the CMA issued a guidance note setting out its views about how the law operates in relation to refunds.
Where a contract is not performed as agreed, the CMA considers that in most cases, consumer protection law will generally allow consumers to obtain a refund.
This includes the following situations:
- Where a business has cancelled a contract without providing any of the promised goods or services
- Where no service is provided by a business, for example because this is prevented by Government public health measures
- A consumer cancels, or is prevented from receiving any services, because Government public health measures mean they are not allowed to use the services.
In the CMA’s view, this will usually apply even where the consumer has paid what the business says is a non-refundable deposit or advance payment.
This positon reflects the CMA’s previous guidance which they had issued in relation to the requirement of fairness in consumer contracts under the Consumer Rights Act 2015, which was that a clause in a contract that gives a blanket entitlement to a trader to cancel a contract and retain deposits paid is likely to be unfair, and therefore unenforceable – it would be unfair to a consumer to lose their deposit if the contract is terminated without any fault on their part, and if they had received no benefit for the payments made.
The CMA’s latest guidance therefore confirms their view that the Covid-19 outbreak does not change the basic rights of the consumer, and that they should not have to pay for goods or services that they do not receive.
The Home Office has not stated when it will end these temporary measures, albeit it has stated that it will provide a warning. Where employers have carried out checks using the temporary measures, the Home Office has confirmed that it will require employers to carry out retrospective checks on any of the following:
- Employees who started working for you when the temporary measures were in place
- Employees who required a follow up check during the temporary measures (for example because their previous leave was coming to an end).
It is not explicit from the guidance but these retrospective checks must require you to have in your possession the physical ID in its original form. When carrying out the retrospective check, employers must record this using the following wording “the individual’s contract commenced on [insert date]. The prescribed right to work check was undertaken on [insert date] due to Covid-19.”
These further checks must be made within eight weeks of the temporary measures ending, and employers must keep records of both checks undertaken. Where the employer discovers that the employee does not have the right to work during the retrospective check they should stop employing them.
As we all adjust and adapt in line with the Government’s guidance throughout this uncertain time, we must consider how we can revise current processes and implement new ones to maintain effective and compliant ways of working. We have identified several key issues that all housing providers should consider.
Protocol Compliance
Housing providers will continue to receive new disrepair claims. Throughout the disruption caused by coronavirus, landlords will still be expected to respond to these claims and comply with the Pre-Action Protocol for Housing Conditions Claims whilst doing so. We address the issue of disclosure in particular below.
Letters of claim will continue to be sent by post to your Registered Office, and the deadlines will run from the date of deemed service. Ensure you have systems to enable you to scan correspondence and forward it to the responsible officer who will handle the claim so deadlines are met.
Under the Protocol, the deadline for disclosure is 20 working days from deemed service of a letter of claim (2 working days after it is sent). So, for example, a letter dated 2 March 2020 would be deemed served on 4 March 2020 and disclosure would therefore be due by 1 April 2020. All housing providers must continue to comply with the Protocol and so landlords should begin preparing now.
Failure to meet deadlines often result in the issuing of further applications to court by tenant’s solicitors which in turn will lead to unnecessary costs orders against landlords.
Therefore, all records, particularly relating to customer contact and repair logs, should be held electronically. If required, this will allow for such documentation to be redacted for GDPR purposes remotely and disclosed to the tenant’s solicitor simply and efficiently.
Remember it is possible to request an extension to all Protocol deadlines and it is inevitable in these unusual times, this will need to be utilised, and should not be refused. Request extensions to deadlines at the earliest opportunity to enable an achievable timescale. It would be a difficult lawyer that would not agree to such a request.