Skip to content

What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision

Related FAQs

Can employees on fixed-term contracts be furloughed?

Yes. Their contracts can be renewed or extended during the furlough period without breaking the terms of the scheme.

If the employee’s contract has not already expired, the contract can be extended or renewed. The employee may be furloughed provided that they were employed on or before 30 October 2020. You must also have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.

If the employee’s contract expired on or after 23 September 2020, the employee can be re-employed and furloughed. Please note that the employee must have been employed by you on 23 September 2020 and you must have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.

 

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Does Force Majeure apply to the leasing of commercial property?

Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.

If you have to undertake collective consultation do you also have to carry out individual consultation?

Once the collective process concludes, an employer can make the decision to proceed with the restructure. They will then have 1-on-1 meetings with employees about the impact of the restructure on them. This will include consideration of alternative employment. There is no need to consult further about the proposal, merely the effect of the restructure on the individual.

Do you need to use HMRC's CEST tool?

CEST stands for Check Employment Status for Tax and, although this should do exactly what is says on the tin, there has been criticism of its accuracy and effectiveness. The CEST tool does not test whether there is ‘mutuality of obligation’ in the relationship which is a key factor in determining status.

You are not obliged to use CEST if you are happy with your own assessment process. If you do use CEST keep a record of the certificate given at the end of the assessment and keep this on the contractor’s file. HMRC will stand by the outcome of a CEST assessment provided the information has been honest and accurate. However, you must have entered information honestly to rely on it – you can’t just say what you want to get the right answer, as HMRC may test what you have said.  Also, many people are unhappy with the CEST tool and consider it leans too much towards employed status.