What is the difference between individual and collective consultation?
Where it is envisaged that 20 or more employees will be dismissed at a relevant establishment within a 90 day period or less, then collective consultation is required (in addition to individual consultation) and the company must inform BEIS (using form HR1).
If there are less than 20 dismissals then you are only required to carry out individual consultation.
Related FAQs
Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.
Sections of the video and their timings are as follows:
(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)
(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II
(05.36) – bounce back loans have been a distraction
(06.27) – muted impact of fintech CBILS lenders
(07.52) – discussion about invoice discounting
(11.59) – looming insolvency environment
(12:52) – emerging themes
The Cabinet Office has published a helpful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). This can include making advance payments to suppliers, if necessary. The PPN sets out actions that public sector bodies should take (until at least 30 June 2020) to ensure continuity of service and to ensure that its suppliers can resume normal contract activity once able to.
The actions public sector bodies should be taking include:
- Informing its suppliers (that they believe are at risk) that they will continue to be paid as normal until the end of June 2020 (even if service delivery is currently interrupted). Risk might include supply chains collapsing and/or significant financial implications for a supplier
- If a contract involves a payment by results mechanism, basing payments on previous months (e.g. the average monthly payment over the previous 3 months), and
- Ensuring that invoices submitted by suppliers are paid immediately to maintain cash flow in the supply chain and help to protect jobs.
If you are a supplier to a public sector body, you must act transparently and on an open-book basis, making cost data available to your public sector clients. You must also continue to pay your employees and subcontractors / suppliers. Suppliers to the public sector must not expect to make profits on any undelivered elements of a contract. The PPN makes clear that, should suppliers be found to be taking undue advantage, or failing to act transparently, a public sector body can take action to recover payments made to that supplier.
The PPN requires public sector bodies to urgently review their contract portfolios and take steps to support suppliers who they believe are “at risk”. However, no definition of “at risk” is given in the document. We would suggest that if you are a supplier and you have yet to hear from a public sector client, you should seek to get in touch with them as soon as possible, particularly if you have concerns about your supply chain, staff retention and/or are experiencing financial difficulties currently. Given the requirement for transparency, you may be required to provide evidence, so it may be helpful to have any relevant documentation ready to send, if necessary, as this may help ensure a decision is made by the public sector client more promptly, particularly as the public sector body may have a number of contracts to consider.
Maintenance Orders embodied in a Court Order are variable. If you have lost a very large part of your income, then the Courts ought to take that into consideration when looking at a Court Application to reduce or end spousal maintenance payments. The outcome of any Court Application will, however, depend on a number of factors.
Technically, you should not just stop paying or reduce the maintenance payments, as your ex-spouse could then make an Application to Court for enforcement and payment of the arrears. You could ask the Court to forego you having to pay those arrears if you had evidence to prove that you could not make the payments, however, the Court will need to take a fair approach and you should not assume this request will be agreed.
You should first try to negotiate a reduction or termination of the maintenance with your ex-spouse, either directly or through a Solicitor. If this is possible, you should obtain a Court Order reflecting that agreement. Where a sensible compromise cannot be reached, a Court Application may be necessary.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.
So the short answer is yes.