Skip to content

What is the guidance in relation to the Mental Capacity Act 2005 and Deprivation of Liberty Safeguards during the Covid-19 pandemic?

The Department of Health & Social Care has published guidance for hospitals, care homes and supervisory bodies on the Mental Capacity Act 2005 (MCA) and Deprivation of Liberty Safeguards (DoLS) during the coronavirus pandemic.

In many scenarios created or affected by the pandemic, decision makers in hospitals and care homes will need to decide:

  • if new arrangements constitute a ‘deprivation of liberty’ (most will not), and
  • if the new measures do amount to a deprivation of liberty, whether a new DoLS authorisation will be required (in most cases it will not be).

If a new authorisation is required, decision makers should follow their usual DoLS processes, including those for urgent authorisations.

A summary of the key points to be taken from the guidance is outlined below:

Use of the MCA and DoLS due to Covid-19

  • During the pandemic, the principles of the MCA and the safeguards provided by DoLS still apply.
  • It may be necessary to change the usual care and treatment arrangements, for example to provide treatment for people with Covid-19, to move them to a new hospital or care home to better utilise resources or to protect them from becoming infected.
  • All decision makers are responsible for implementing the emergency Government health advice  and any decision made under the MCA must be made in relation to a particular individual, it cannot be made in relation to groups of people.

Best interest decisions

  • In many cases, a best interests decision will be sufficient to provide the necessary care and treatment for a person who lacks the capacity to consent to the care and/or treatment arrangements during this emergency period.
  • If an individual has made a valid and applicable advance decision to refuse the treatment in question, then the relevant treatment, even for Covid-19, cannot be provided.

Delivering life-saving treatment

  • Where life-saving treatment is being provided in care homes or hospitals, including for the treatment of Covid-19, then the person will not be deprived of liberty as long as the treatment is the same as would normally be given to any person without a mental disorder.
  • The DoLS will therefore not apply to the vast majority of patients who need life-saving treatment who lack the mental capacity to consent to that treatment, including treatment to prevent the deterioration of a person with Covid-19.

The full guidance can be found here.

Related FAQs

What should I do about non-urgent repairs?

As discussed above, Covid-19 will inevitably deplete the workforce of housing providers in the foreseeable future. It would be prudent to consider making short-term policy changes to deal with this situation and manage the expectations of tenants going forward. A key policy change to consider is the extension of the standard lead-time for completing all non-urgent repairs and inform tenants of this change.

Such a change will also reduce pressure on landlords and front-facing staff.

As above, employers must protect the interests of their staff, particularly regarding health and safety. Extra care should be exercised when assessing the level of emergency of a repair on a case by case basis. All efforts should be made to reduce the number of attendances at properties by repair staff, whilst keeping all tenants safe.

As ever, communication is key – the pandemic cannot be used as a blanket excuse for abstaining from all duties and obligations. Housing providers must take a pragmatic approach in safeguarding customers whilst considering the interests of is workers. Maintaining lines of communication with all parties remains paramount.

Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Is the Land Registry functioning?

Yes. The Land Registry published a new service update on 14 May, here:

https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service

Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

To summarise some further points:

  • Most information enquiries are experiencing minimal delays
  • Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
  • Cancellation dates for replying to requisitions are extended until further notice
  • Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
  • Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
  • Requests for extensions to a notice or objection period will be granted if lawfully possible
  • Land charges searches can be submitted electronically with PDF documents
How do I set the hours that my employees will work under the Flexible Furlough Scheme?

Employers and employees can decide the split of the hours of work and the hours of furlough. There is no maximum or minimum requirements. You can change the arrangement, by agreement, from time to time.

When claiming for employees who are flexibly furloughed, you should not claim until you are sure of the exact hours they will work during the claim period.