Skip to content

What is the “Job Retention Bonus”?

As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.

Related FAQs

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Is it legally enforceable?

The guidance is non-statutory and is not binding on business. However, businesses should be aware that there might be reputational consequences if they do not follow the guidance; we have already seen in the context of taking advantage of furlough funding that not being in breach of the law is no protection against negative publicity. Further to the extent a contract expressly requires parties to act reasonably, it could be expected that this guidance is one of the factors a court would consider in determining what is reasonable.

What criteria will HMRC use to assess applications for furlough from publicly funded organisations?

The government released further clarification on the Coronavirus Job Retention Scheme on 4 April. The wording referred to concerning public sector organisations and organisations receiving public funding remains the same.

The revised guidance does provide a helpful insight into how HMRC will deal with applications made to it for assistance under the scheme. It appears that there won’t be a particularly forensic approach adopted by HMRC. The guidance says you can furlough staff if you cannot maintain your current workforce because your operations have been severely affected by coronavirus.

It goes on to say that all employers are eligible to claim under the scheme and the government recognises different businesses/organisations will face different impacts from coronavirus. The need to demonstrate the impact of coronavirus on your business/organisation is not one of the criteria businesses/organisations are going to need to satisfy, so the government does not appear to intend to set a specific test to determine if a business/organisation is “severely impacted by coronavirus”. It is hoped that this should provide additional comfort to publicly funded organisations facing significant restrictions to their operations during the Covid-19 crisis.

What facilities are available under CBILS?

Lenders implementing the Scheme can assist in a number of ways, including:

  • Term loans
  • Overdrafts
  • Invoice finance
  • Asset finance facilities

The maximum value available under the scheme is £5m, with repayment terms of up to six years for term loans and asset finance. Overdrafts and invoice finance facilities will be available for up to three years.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.