What is the “Job Retention Bonus”?
As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.
Related FAQs
The Government guidance does not require any business to close except some non-essential shops and public venues, so in theory, all businesses can continue to occupy and operate from their existing premises. However, government guidance strongly encourages businesses to arrange for everybody able to work from home to do so. The majority of office sector business will fall into this category.
In the industrial sector, the majority of businesses will not be able to operate via home working and will, therefore, need to retain employees on site though in some cases this may be able to be scaled back.
Any tenants continuing to operate from their premises should consider whether or not they need to make any alterations to the premises to facilitate social distancing of employees and whether or not such works would require a consent from the Landlord under the terms of the lease.
The Government will provide the lender with a partial guarantee (80%) against the outstanding facility balance, subject to an overall cap per lender. Note, the Government guarantee is to the lender only, the borrower will always remain 100% liable for the debt.
We understand that will make an initial claim for recovery against the borrower and will, once its normal recovery procedures have been completed, claim against the Government guarantee.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf