Skip to content

What is the new Permitted Development Right for restaurants, cafes and drinking establishments?

A new Permitted Development Right has been introduced providing restaurants and cafes, drinking establishments with expanded food provision to temporarily provide takeaway food. The new right came into force on 24 March 2020 and expires on 23 March 2021. The right is subject to three conditions:

  • The developer must notify the local planning authority if the building and any land within its curtilage is being used, or will be used, for the provision of takeaway food at any time during the relevant period
  • Change of use to the provision of takeaway food under the Right, does not affect the use class which the building and any land within its curtilage had before the change of use
  • If the developer changes use to the provision of takeaway food under the Right, the use of the building and any land within its curtilage reverts to its previous lawful use when the Right expires or, if earlier, when the developer ceases to provide takeaway food.

Alcohol will still be subject to the same licensing requirements. At this stage, it is not clear how the Right will interact with any current planning conditions placed on an establishment.  Enforcement however remains discretionary. A link to Statutory Instrument 2020 No.330 is below.

http://www.legislation.gov.uk/uksi/2020/330/made

Related FAQs

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
How have competition law rules been relaxed in the light of the coronavirus outbreak?

The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What type of matters are the Courts still dealing with?

Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:

Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).

Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.

The full guidance can be found at:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/881019/Civil_court_listing_priorities_24_April_2020.pdf

When will I receive a grant under this scheme?

The Chancellor confirmed that payments under the scheme would not be available immediately.