What is the NICE guidance around clinical decision-making?
- Be alert to the fact that guidance on treating Covid-19 may change with emerging knowledge/scientific data and this may require subsequent modifications to treatment.
- Critical care staff should support healthcare professionals who do not routinely work in critical care but need to do so.
Related FAQs
If an employee is required under government guidance to wear a face mask during the course of their employment and there is no applicable exemption, any fine issued would be payable by the employee, not the employer.
The golden thread requirements will be retrospective, so will apply to existing buildings as well as new build. This is part of the reason for the Building Safety Regulator’s ‘get to know your building’ guidance referred to in the talk, with the link in the Powerpoint presentation. While the details of the golden thread requirement are still to be confirmed, now is a good time to start to gather as much information as can be obtained about existing buildings as possible in preparation. The Government guidance anticipates that the Principal Accountable Person will be responsible for developing and coordinating the golden thread for existing buildings.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
We are working with many of our clients to progress with stopping up applications in order to divert/stop up highways and public rights of way affecting development sites. Due to lockdown restrictions the Department for Transport stalled the progress of applications because they were unable to comply with the statutory publicity requirements. We have very recently been contacted by the Department for Transport casework team who have confirmed that the stopping up/diversion applications can now be progressed. We are aware that Councils across the country are also now progressing with applications. Please contact us if you require any advice/assistance in respect of your application.