What measures can be taken without notification to the European Commission?
There have always been ways for public bodies to assist without being required to notify these for approval. These continue to be available during the financial crisis, and are likely to be increasingly useful for measures which need to be introduced quickly. The measures include:
Those where it is possible to conclude that there is no effect on trade between Member States – for example, measures which are likely to have only a limited local effect. The European Commission has concluded, for example, that measures to assist locally-focused cultural activity can be assumed to have no effect on inter-State trade.
Those where it is possible to conclude that the State is acting in a way consistent with a commercial operator (the so-called Market Economy Operator Principle) – particular care will need to be taken in the context of current economic conditions to ensure that it can reasonably be asserted that a commercial operator would act in the same way as the public body.
Measures under the General Block Exemption Regulation – this legislation allows various types of aid, or aid schemes, to be employed.
Examples include aid for SMEs, aid for research and development, aid for local infrastructure and aid to ports and airports.
De Minimis Measures – Member States are permitted to grant small amounts of aid to undertakings over three fiscal years (the current year and the previous two years). This allows undertakings to receive up to €200,000 (or €500,000 where they are providing public services).
Related FAQs
The law says that if after assessing a risk and considering all the control measures available to you, you cannot undertake a task safely – then you should not undertake the task.
If that means taking BAME workers out of higher risk frontline work, that is what will have to be done.
Beware of workers saying “we’ll accept the risk” – it does not protect you against regulatory/enforcement action or civil claims.
The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.
Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance, in the event that the customer enters an insolvency procedure.
This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.
Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.
Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
On 7 May the Government published guidance on how contracting parties can act responsibly in order to assist the effort to deal with Covid-19. The guidance seeks to persuade contracting parties to act reasonably and recognise the impact of Covid-19 on contractual counterparties. This will continue to be relevant as business begins to emerge from lockdown.
The application has to be made before the date on which the accounts should have been filed, so this process can’t be used if you are already late. If you don’t make the application before your filing deadline, then a fine will automatically be generated if your accounts are filed late. Whilst you could appeal against such a fine on the grounds that the delay was caused by coronavirus issues, this is likely to be a much more time consuming and uncertain process that applying in advance.
It does not appear that the process applies to Confirmation Statements or other returns.