What measures can be taken without notification to the European Commission?
There have always been ways for public bodies to assist without being required to notify these for approval. These continue to be available during the financial crisis, and are likely to be increasingly useful for measures which need to be introduced quickly. The measures include:
Those where it is possible to conclude that there is no effect on trade between Member States – for example, measures which are likely to have only a limited local effect. The European Commission has concluded, for example, that measures to assist locally-focused cultural activity can be assumed to have no effect on inter-State trade.
Those where it is possible to conclude that the State is acting in a way consistent with a commercial operator (the so-called Market Economy Operator Principle) – particular care will need to be taken in the context of current economic conditions to ensure that it can reasonably be asserted that a commercial operator would act in the same way as the public body.
Measures under the General Block Exemption Regulation – this legislation allows various types of aid, or aid schemes, to be employed.
Examples include aid for SMEs, aid for research and development, aid for local infrastructure and aid to ports and airports.
De Minimis Measures – Member States are permitted to grant small amounts of aid to undertakings over three fiscal years (the current year and the previous two years). This allows undertakings to receive up to €200,000 (or €500,000 where they are providing public services).
Related FAQs
The current situation with the coronavirus pandemic has presented obvious challenges to the effective and fair operation of the Court of Protection (COP). Remote access to the COP has therefore become a necessity to ensure that hearings continue to provide proper access to justice. All parties involved in such cases have a responsibility in achieving this primary aim.
Hopefully, further guidance will provide additional clarification on this, but it is difficult to see how a charity whose operations have been significantly curtailed because of the Covid-19 restrictions, cannot furlough employees and access the scheme, in particular where they have several different income streams. For example if a charity’s retail or fundraising operations have been significantly curtailed due to the restrictions, then it would appear unfair for it not to able to rely on the furlough scheme to assist in the funding of the employment costs associated with this part of the charity.
However, it might be prudent, where there are services that are publicly funded and employees working within those services cannot undertake their normal work, to consider if they can do different roles to work on Covid-19 activities. If there is no such work available then the guidance does appear to allow the furloughing of employees and such organisations to access the scheme.
In our experience, the funding streams and work undertaken by the organisations that could fall into the third category identified above can be exceptionally diverse and we would strongly recommend that you take advice before making such decisions about furloughing employees.
As long as you can demonstrate that you have exercised reasonable care in determining status you have discharged your obligations in that respect. However, if you are unable to demonstrate this, you may as the end user client be responsible for the contractor’s tax and NIC’s.
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.