What options do I have if I have staff with childcare responsibilities but their job cannot be done at home?
If it is not possible to find work for the employee to do at home, you do have the option of putting the employee on furlough.
Related FAQs
Under usual rules, workers are entitled to a minimum of 28 days holiday including bank holidays, each year. Except in limited circumstances, it cannot be carried between leave years meaning that workers lose their holiday if they do not take it.
The government passed emergency legislation relaxing the carry-over of the 20 days leave entitlement provided under EU law. Where it is not reasonably practicable for an employee to take leave in the relevant leave year as a result of the effects of the coronavirus then they could be entitled to carry over the untaken leave into the next year.
If there is a court order then this should be complied with, unless you are unable to do so because the parent with whom the child lives is self-isolating, the other parent is self-isolating or the children are showing symptoms of the virus. If you are unable to comply with the court order, the other parent should be notified immediately in writing and proposals put forward for how they can see and speak to their children by telephone, FaceTime, Zoom or some other method.
If any necessary variations to the arrangements cannot be agreed then you should contact us for legal advice.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved