What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Related FAQs
Whilst it is acknowledged that doctors may be working in unfamiliar circumstances or surroundings, or in clinical areas outside their usual practice. Doctors should consider the best course of action to take in these circumstances by utilising the following:
- What is within their knowledge and skills
- What support other members of the healthcare team could offer
- What will be best for the individual patient given available options
- The protection and needs of all patients they have a responsibility towards
- Minimising the risk of transmission and protecting their health.
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Government guidance is that public transport should be avoided wherever possible. Transport providers will be expected to follow government guidance to make their services more COVID-19 secure.
- Start critical care treatment with a clear plan of how the treatment will address the diagnosis and lead to agreed outcomes.
- Review critical care treatment regularly and when the patient’s clinical condition changes.
- Stop critical care treatment when it is no longer considered able to achieve the desired outcomes. Record the decision and the discussion with family, carers and the patient (if possible).