What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Related FAQs
An employee can refuse to attend work but their refusal to do so will have to be based on a reasonable belief that their health and safety is in danger. Whether or not their refusal is reasonable will take into consideration factors such as the employee’s own health and whether they are at a higher risk of becoming seriously ill if they contract Covid-19 and the steps their employer has out in place to mitigate the danger of contracting Covid-19 at work.
In such circumstances where the employee’s belief is deemed to be reasonable, they will be entitled to stay at home and receive full pay.
If an employee is subsequently dismissed for refusing to attend work in these circumstances, they may be able to bring a claim for unfair dismissal.
It is possible to review working arrangements for contractors before the new rules come into effect. This will require immediate action.
You could consider terminating current contracts and entering into new terms that reflect working arrangements for a self-employment arrangement.
Another possibility is encouraging contractors to abandon the PSC model and provide services under a compliant umbrella company.
In the event of a determination of employed status you should seek to enter new terms that at the very least reflect the new tax arrangements .
Employers who have apprentices on fixed-term contracts due to end during the pandemic should discuss arrangements with the apprentices including whether an extension to the contract can be offered to allow them to complete their apprenticeship.
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
No one factor will determine status and the outcomes will differ depending on the nature of the work being carried out and the business of the end user client.
When you have carried out an assessment based on the relevant factors you can either get in touch with us to discuss further, check your answers against HMRC’s CEST tool or do both before making a final determination.