Skip to content

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

Related FAQs

What other factors may be considered?
  • Integration:
    • Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
  • Exclusivity:
    • Is the contractor restricted from working for other organisations without the consent of the end user client?
  • Length of engagement:
    • Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
  • Pay:
    • Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
  • Facilities:
    • Does the contractor provide their own equipment and materials to provide the services?
  • Financial risk:
    • Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?
What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
How are civil hearings being conducted?

The majority of hearings are taking place by video or phone.

Court guidance has been issued on telephone and video hearings during the coronavirus outbreak:

https://www.gov.uk/guidance/hmcts-telephone-and-video-hearings-during-coronavirus-outbreak

Where a Judge orders “teleconferencing”, it will take place using BTMeetMe, or video conferencing using Skype for Business or Cloud Video Platform.

All hearings are subject to the relevant jurisdictional rules and practice directions and usual court etiquette, including wearing appropriate attire and not eating or drinking during a hearing.

Electronic bundles of documents and authorities (if required) need to be prepared, indexed and paginated and sent to the Court well in advance of any hearing.

What are the negatives associated with having MHFAs in the workplace and what is the best way to manage this without removing MHFAs from the company?

The only potential negatives are the potential for MHFAs to become overloaded, or for MHFAs to overstep the boundaries of their role. Both would be avoided if a suitable framework is in place around them, and if adequate ongoing support and training is provided.

Am I obliged to offer staff flexible furlough?

No, there is no obligation on employers to offer a flexible furlough arrangement to staff. Operationally, flexible furlough may not be appropriate for your business and equally, returning on a part-time basis may not be suitable for individuals already furloughed for various reasons. Concerns about returning to work part-time or at all should be considered on a case-by-case basis.