What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Related FAQs
Some employers falling into the third group of organisations described above could understandably feel aggrieved that on the first reading of the guidance they are not able to furlough employees and rely on the Government scheme. Many publicly funded organisations that are not public sector employers, receive a package of public funding with little expectation on how that funding is used or applied, other than broadly for it to be used in providing the services it is contracted to deliver. Also, several publicly funded organisations have many different income streams and the element of funding that is received from the public purse can be only an element of their operating costs.
Unfortunately there is still no clear guidance on when employers falling into the third category identified above can use the scheme. The only reference in the guidance on this states that where organisations are not “primarily funded” from the public purse and whose staff cannot be redeployed to assist with the coronavirus response, the scheme might be appropriate to be used for some staff. This seems to suggest that where an employing organisation is not wholly or mainly funded by public funding and staff cannot be redeployed to work in areas in the effort to combat coronavirus, then it would be appropriate for the employer to access the scheme.
If considering applying for grants under the scheme a sensible approach would be to look at the combined total of your public funding and payments under the scheme and make sure it will not represent more than 100% of the level of total income you would have expected to receive during this period in a non-Covid scenario.
Local Authorities are expected to maintain support to suppliers and this should be considered:
For the purposes of collective consultation, making someone redundant and/or changing terms and conditions of employment, by termination and re-engagement, is also classed as a dismissal by reason of redundancy and so has the exact same consultation requirements.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Partners Damien Charlton and Jane Garvin look at the provisions of the Bill which impact on a supplier’s rights under a contract when their customer enters an insolvency procedure. They also outline other changes to insolvency procedures that the new law will introduce.
This webinar is part of a series designed for in-house lawyers. If you would like to register to receive invitations to future events for in-house legal counsel, please email damien.charlton@wardhadaway.com.
As above, employees must not leave their home unless they have a ‘reasonable excuse’.