What should an employer do when an employee has been told to self-isolate under the coronavirus Test and Trace scheme?
- Do not require them to work
- Continue to communicate with and support them
- Allow them to work from home, is there alternative work for them to do if they can’t do their work from home
- Offer SSP or allow them to take holiday if they want to.
Related FAQs
No. This bill relates to corporate insolvencies only. Should you require any advice as to personal insolvency situations, please contact our team.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
The guidance is non-statutory and is not binding on business. However, businesses should be aware that there might be reputational consequences if they do not follow the guidance; we have already seen in the context of taking advantage of furlough funding that not being in breach of the law is no protection against negative publicity. Further to the extent a contract expressly requires parties to act reasonably, it could be expected that this guidance is one of the factors a court would consider in determining what is reasonable.
It is possible to review working arrangements for contractors before the new rules come into effect. This will require immediate action.
You could consider terminating current contracts and entering into new terms that reflect working arrangements for a self-employment arrangement.
Another possibility is encouraging contractors to abandon the PSC model and provide services under a compliant umbrella company.
In the event of a determination of employed status you should seek to enter new terms that at the very least reflect the new tax arrangements .
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at: