What should I do about non-urgent repairs?
As discussed above, Covid-19 will inevitably deplete the workforce of housing providers in the foreseeable future. It would be prudent to consider making short-term policy changes to deal with this situation and manage the expectations of tenants going forward. A key policy change to consider is the extension of the standard lead-time for completing all non-urgent repairs and inform tenants of this change.
Such a change will also reduce pressure on landlords and front-facing staff.
As above, employers must protect the interests of their staff, particularly regarding health and safety. Extra care should be exercised when assessing the level of emergency of a repair on a case by case basis. All efforts should be made to reduce the number of attendances at properties by repair staff, whilst keeping all tenants safe.
As ever, communication is key – the pandemic cannot be used as a blanket excuse for abstaining from all duties and obligations. Housing providers must take a pragmatic approach in safeguarding customers whilst considering the interests of is workers. Maintaining lines of communication with all parties remains paramount.
Related FAQs
The government has stated that the scheme will apply to apprentices and that they can continue to train whilst they are furloughed. However you must pay at least the Apprenticeship Minimum Wage, National Living Wage or National Minimum Wage for all periods of training during furlough leave, taking into account the rate increases from 1 April 2020 and the increases which will take effect from 1 April 2021. This means that you will be responsible for any shortfall in the amount claimed under the scheme and the appropriate minimum wage.
We recommend that you get in touch to discuss any queries on furloughing apprentices.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.
If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).
The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Employees continue to accrue leave during furlough (whether they are on full furlough or flexible furlough) and can take leave during periods of Flexible Furlough (so long as you top the grant up to full pay for any days taken as holiday).
Government guidance has been updated to state that “Employees should not be placed on furlough for a period simply because they are on holiday for that period.” If a period of furlough happens to coincide with an employee’s holiday then you should ensure that there are business grounds to support furlough being used in that instance so that it isn’t just being used as a means to fund holiday utilisation.