Skip to content

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements

Related FAQs

What about someone who refuses because they are against the vaccine (the anti-vaxers)?

It is a theoretical possibility that “anti-vax” beliefs could be a philosophical belief under the Equality Act 2010 and therefore anti-vaxers have the right not to be discriminated against for their beliefs. Much will depend on why the individual is against the vaccine. Conspiracy theorists (the vaccine is being used as an opportunity to monitor you or it’s all because of 5G) are highly unlikely to be treated as having a philosophical belief!

What are the new Procurement Policy Notes (PPN)?

The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.

PPN 01/20: Responding to COVID-19

The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.

This PPN provides guidance for the following circumstances:

  • Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
  • Direct award due to an absence of competition or protection of exclusive rights
  • Call off from an existing framework agreement or dynamic purchasing system
  • Call for competition using a standard procedure with accelerated timescales
  • Extending or modifying a contract during its term

PPN 02/20: Supplier relief due to COVID-19

PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.

This PPN provides guidance for the following circumstances:

  • Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
  • Put in place appropriate payment measure to support supplier cash flow
  • Where contract payments are based on ‘payment by results’ make payments based on previous invoices
  • Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
  • Ensure invoices submitted by suppliers are paid immediately on receipt

PPN 03/20: Use of Procurement Cards

The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.

This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:

  • Increase a single transaction limit to £20,000 for key card holders
  • Raise monthly limits on spending with procurement cards to £100,000 for key card holders
  • Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs

Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.

The PPN also advises that by 30 April 2020, in scope organisations should:

  • Ensure that a number of appropriate staff have the authority to use these cards
  • Open all relevant categories of spend to enable these cards to be used more widely
What impact does the Regulations have in respect of matters which arise from Fire Safety Audits - e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?
The duty would fall on the owner of the building to control the hazards presented by balconies made from combustible materials. There may be scope (via warranties/indemnities or other terms) arising from the contract between the developer and owner for the owner to seek to recover the cost of remedial works.
How should contracting authorities work with PFI providers?
  • Working with PFI providers to get contingency plans up to date
  • If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
    • maintain unitary charge payments
    • revise contract requirements/standards

moderating payment and performance regimes where appropriate.

  • In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
  • When putting local bespoke arrangements into place it is vital that:
    •  Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
    • It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
Will HM Treasury continue to collect my apprenticeship levy payments?

HM Treasury have no current plans to pause the collection of apprenticeship levy payments from employers, therefore levy-paying employers must continue to make payments. There is also no plan to extend the 24 month period allowed to spend levy funds.