What should I do if contractor insolvency occurs?
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Related FAQs
Almost two thirds of hearings conducted in the Civil Court will occur in person over the next few months as the Civil Court sees an influx in cases.
The Courts
In the Business & Property Courts, cases have been dealt with consistently since the start of the pandemic, except for trials that run for longer than 10 days in the Commercial & Admiralty Court. The Queen’s Bench Division and Administrative Court are also running as normal. If your case is listed for one of these courts, you do not need to be concerned that your case may take longer than anticipated, with conclusions still being reach at the normal rate.
Hearings
Since the start of the pandemic, most hearings have been conducted online through various platforms such as Skype for Business and Cloud Video Platform. The courts are of the view that remote hearings tend to take longer than those that are held in person. As a result, if your case is due to be held in person, the case may be heard in less time. HM Courts and Tribunals Service stated that:
“Wherever possible we will look to facilitate face-to-face hearings, but our expectation is that remote hearings will continue to play an important role for the foreseeable future, given that social distancing will continue to limit courtroom capacity compared to pre-Covid levels.”
More courtrooms have become available since the start of the pandemic, resulting in more facilities for cases to be heard in person, which will have the aim of helping to rid of the backlog of cases, along with remote hearings being conducted too, which is a welcome step forward.
Approximately 300 additional support staff will be employed for remote hearings before the end of 2020, enabling better service with remote hearings. The Government has decided that some civil judges will have the option to extend operating hours for cases to be held in the evenings and on weekends too, which may be most suitable for small and fast-track claims, resulting in a potentially faster outcome. The efficiency of all the new measures are being monitored and changes are being implemented, such as increasing the capacity of the Small Claims Mediation Service.
Small Claims Mediation Service
With claims of a lower value, a high proportion of cases successfully settle outside of court, therefore, if you have a small claim, the mediation service may be suitable for your case. Mediation involves a trained impartial third party, with the parties to the case discuss the dispute with the assistance of the third party, aiming to reach a settlement. Now with the increased capacity, it may make the mediation service more accessible, meaning that an agreement can be reached more swiftly rather than waiting for the matter proceed to a hearing.
The courts have stated that:
“We aim to increase capacity to accommodate 90% of parties who want mediation, rather than the current 40%. We are recruiting additional mediators and restructuring ways of working to achieve this.”
This is a positive shift for those with small and fast-track claims where legal costs ought to be kept to a minimum. Settling by mediation removes the need for trial costs, amongst other costs, and has additional benefits such as the matter being dealt with more amicably.
Transparency is considered to be central to the philosophy of the COP. The guidance provides details on issues concerning transparency of proceedings and involvement/attendance of P. Whilst there will be some difficulties with ensuring that remote hearings are accessible to the public as an ‘open court’, provisions have been made for the continued presence of the press where the facilities can accommodate this.
A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.
Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
We are working with many of our clients to progress with stopping up applications in order to divert/stop up highways and public rights of way affecting development sites. Due to lockdown restrictions the Department for Transport stalled the progress of applications because they were unable to comply with the statutory publicity requirements. We have very recently been contacted by the Department for Transport casework team who have confirmed that the stopping up/diversion applications can now be progressed. We are aware that Councils across the country are also now progressing with applications. Please contact us if you require any advice/assistance in respect of your application.