What should I do if contractor insolvency occurs?
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Related FAQs
The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.
Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance, in the event that the customer enters an insolvency procedure.
This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.
Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.
Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.
Those individuals who are already exempt from the existing face covering obligations, will continue to be exempt from the new rules. These include:
- Those unable to put on or wear a face covering because of a physical or mental illness or disability
- People for whom wearing or removing a face covering will cause severe distress
- Anyone assisting someone who relies on lip reading to communicate
- Be alert to the fact that guidance on treating Covid-19 may change with emerging knowledge/scientific data and this may require subsequent modifications to treatment.
- Critical care staff should support healthcare professionals who do not routinely work in critical care but need to do so.
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.
Sui generis uses are not within any Use Class. Consequently planning permission is required for the:
- Change in the use to a sui generis use
- Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class
Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.
Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.
Depending on the form of the enforcement action, there could be a right of appeal.