Skip to content

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements

Related FAQs

What if I have missed the January deadline for submitting my 2018/2019 tax return?

You had until 23 April 2020 to submit your return in order to be considered for eligibility.

What if a contractor is deemed to be employed?

The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.

If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.

What is the most important thing employers should do from a health and safety perspective?

Conduct risk assessments! Your RA must cover every foreseeable risk arising from a return to the workplace, including the impact of reduced staff levels and any operational/administrative changes necessary to ensure social distancing.

Appropriate steps should be taken to manage and mitigate identified risks. Where this is not possible, businesses need to decide whether certain activities are necessary for the business to operate or if they can be temporarily put on hold.
Keep a close eye on the comprehensive Government guidance: https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19

In particular focus on social distancing and workplace health measures. This guidance will evolve over time and you will need to be sure that your organisation is sticking to it AND reviewing and updating its risk assessment.

What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.

What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs