Skip to content

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements

Related FAQs

What payments can be included in the claim for a grant?

You can claim for regular payments you are obliged to pay staff such as non-discretionary overtime, non-discretionary fees, non-discretionary commission and piece-time payments. Overtime in this context is referred to as ‘past overtime’ in the updated guidance which would suggest that you should use the variable pay calculation (see FAQ above) for those who regularly carry out overtime.

What is the guidance for doctors working during the pandemic?

The General Medical Council (GMC) have published guidance online for doctors during this time of uncertainty.

 

Alongside this, their website displays guidance for temporary registration to approximately 15,000 doctors, who left the register or gave up their licence to practise in the last three years.

 

These clinicians have been contacted to assist with the growing pandemic, outlining the process they would follow and informing them of their right to opt-out. The Secretary of State for Health can ask the GMC to grant such registration under Section 18a of the Medical Act 1983, in an emergency.

Court proceedings have been issued. What happens to the court timetable?

The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected