What should I do if contractor insolvency occurs?
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Related FAQs
Although these measures fall short of the level of assurance given to employees both in terms of eligibility for an immediacy of access to payments, they are a vast improvement on the support for self-employed workers that has been put in place until now. Current support includes:
- Access to business interruption loans
- Self-assessment tax payments that were due in July 2020 have been deferred until January 2021
- VAT is deferred until the next quarter
- The introduction of Time to Pay arrangements under which deferrals for HMRC payments can be agreed
- The minimum income floor for universal credit has been suspended which will allow self-employed workers to access the equivalent of Statutory Sick Pay (SSP)
- Universal credit and tax credit payments to increase by £1000 per year
Solicitors can be authorised to sign contracts for their clients – a signed letter of authority should be scanned and sent to avoid posting potentially contaminated documents.
Solicitors should exchange supplemental agreements on behalf of their clients to agree to postpone exchange and completion dates if it has been agreed to push these back.
The Law Society advises that electronic signatures be used as much as possible for contracts, to avoid possible contamination. However, the Land Registry confirms that the legal transfer document cannot be validly executed with an electronic signature. Solicitors should agree a completion undertaking that the original transfer document will be sent when received and after the restrictions have been lifted.
The Land Registry’s latest guidance https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-services published on 14 May states:
We accept deeds that have been signed using the ‘Mercury signing approach’.
For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.
Solicitors should be willing to adopt this procedure for completing transactions to enable them to be registered by the Land Registry.
The execution of a transfer is a deed and must be witnessed. Members of the family can witness signatures so long as they are not also a party to the document. A witness will be more credible if they are 18 or over, but this is not a legal requirement. The legal requirement is for the witness “to be present” when the document is signed. It would be possible for a witness to be on the other side of the room or the other side of a window, and validly witness the execution of a deed. The witness does need to take precautions to avoid possible contamination from the document.
A statutory declaration does not need to be witnessed but must be administered by a solicitor or commissioner for oaths. There is no legally prescribed process for this, and there is nothing to suggest that this could not be validly done via a video telephone call if the signature on the declaration can clearly be seen by the person commissioning the oath when the oath is made.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
IR35 is an anti-tax avoidance regime which is intended to tackle (in HMRC’s view) the long standing issue of individual contractors providing their services or labour via an intermediary – which is usually a personal service company (referred to as a PSC). We’ll talk about PSCs here, but there are other types of intermediaries that are caught.
HMRC’s view is that this arrangement is often considered to be disguised employment and therefore a tax-avoidance arrangement.
So IR35 is essentially a test of employment status – and if, once you apply the test, the contractor should be an employee, they should then be taxed as an employee.