Skip to content

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements

Related FAQs

What are the standard holiday rules?

Under usual rules, workers are entitled to a minimum of 28 days holiday including bank holidays, each year. Except in limited circumstances, it cannot be carried between leave years meaning that workers lose their holiday if they do not take it.

The government passed emergency legislation relaxing the carry-over of the 20 days leave entitlement provided under EU law. Where it is not reasonably practicable for an employee to take leave in the relevant leave year as a result of the effects of the coronavirus then they could be entitled to carry over the untaken leave into the next year.

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

When should I apply to extend the period allowed to file accounts?

The application has to be made before the date on which the accounts should have been filed, so this process can’t be used if you are already late. If you don’t make the application before your filing deadline, then a fine will automatically be generated if your accounts are filed late. Whilst you could appeal against such a fine on the grounds that the delay was caused by coronavirus issues, this is likely to be a much more time consuming and uncertain process that applying in advance.

It does not appear that the process applies to Confirmation Statements or other returns.

Would you suggest using a different name for a MHFA, maybe a MH champion, to encompass the wider pro-active role?

This may be a good idea – whatever name they are given, it is essential that MHFAs are empowered to take a proactive approach to organisational mental health and that they have the bandwidth to be able to discharge their responsibilities.  The name should reflect the culture of the organisation, the key aspect is awareness and accessibility – identifying a name for your company that supports this is key.

What is Coronavirus Business Interruption Loan Scheme (CBILS)?

The Coronavirus Business Interruption Loan Scheme (“CBILS“) is open for applications to provide small businesses with a loan of up to £5m to assist with the Covid-19 outbreak. The Scheme is aimed at businesses who are experiencing lost or deferred revenues, and who otherwise would be denied support from lenders, to be supported by a Government backed guarantee. The Scheme will initially run for six months with the possibility to be extended where required, so businesses should only approach a lender under the Scheme as and when they require assistance.