What should I do if contractor insolvency occurs?
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
On 7 May the Government published guidance on how contracting parties can act responsibly in order to assist the effort to deal with Covid-19. The guidance seeks to persuade contracting parties to act reasonably and recognise the impact of Covid-19 on contractual counterparties. This will continue to be relevant as business begins to emerge from lockdown.
The CLC has also prepared a template letter that firms may adopt and issue to their workforce regarding travel to work. This can be accessed at download document.
The CLC’s current advice to those carrying out works on site is to carry out your own risk assessment on each site and determine whether or not it is safe to continue to work in accordance with the Public Health England instructions and the CLC Site Operating Procedures. If it is not possible to work in accordance with the above they should not work.
A number of our clients and networks raised issues in the early stages of the Scheme around the requirement for personal guarantees to access finance under the Scheme. The Scheme has now been updated so that:
- For facilities under £250,000, personal guarantees cannot be taken to support lending under the Scheme.
- For facilities above £250,000, personal guarantees may still be required by a lender but the amount which can be recovered under these guarantees is capped at a maximum of 20% of the outstanding balance of the CBILS facility after taking into account any other recoveries from business assets.
An extension to the traditional business interruption insurance, “contingent business interruption insurance” often covers areas such as business interruption due to damage to property of a customer or suppliers. Nonetheless, proving loss can be problematic.
Claims for loss of use of the property may be possible as a result of forced business closure due to lockdown. Accordingly policies should be carefully reviewed to see if cover is available.