What should I do if I think this is relevant to my contracts?
It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:
- Ensure that initial contact with your counterparty is framed in the correct way
- Ensure that any variations are fully documented so that both parties are fully protected
Related FAQs
Some of these can be implemented by you, some need agreement or consultation and some depend on the wording of contracts. We’ll explain more in relation to each option.
Yes. The Government continues to support the construction industry and the Prime Minister’s recent statement supports the return to work of those who cannot work from home, if they can work safely. This has seen an immediate surge in industry workforce returning to work. Banks and storage and distribution businesses are permitted to operate as essential businesses.
Solicitors and estate agents may still not permit members of the public to enter their premises, but can operate remotely via website, phone, email and other methods, as normal. The Government’s latest guidance published on 13 May now advises that moving house need not be postponed, provided social distancing and safe ways of working can be adopted. Restrictions remain for those who are infected or who are self-isolating or vulnerable, and they should not move house or accept visitors.
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.
Yes, however holiday pay during furlough must remain at the normal rate of pay and not the reduced furloughed rate. You can still claim for this period under the scheme but you will be responsible for any amounts beyond the maximum you can claim. Employers have flexibility to restrict when leave can be taken both during and after period of furlough in the normal way.
If an employee usually works bank holidays then the employer can agree that this is included in the grant payment. If the employee usually takes the bank holiday as leave then you would either have to top up their usual holiday pay, or give the employee a day of holiday in lieu.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.