What technology is being used by the COP for remote hearings?
Interestingly, there is currently no ‘single’ technology to be used by the judiciary within the protocol. The court and parties must choose from a selection of possible IT platforms or audio/telephone hearing (further details available in the guidance e.g. Skype for Business, Microsoft Teams, Zoom etc.) The particular platform must be agreed at the outset of each case and then specified in the case management order. The guidance issued also sets out the basic principles which apply when conducting remote hearings.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The Town and Country Planning (Use Classes) (Amendment) (England Regulations) 2020 were laid before Parliament and come into force on 1 September 2020. They apply in England only.
The changes include the revocation of the following Use Classes;
- A1 – shops
- A2 – financial and professional services
- A3 – restaurants and cafes
- A4 – drinking establishments
- A5 – hot food takeaways
- B1 – business. Also revoked are the sub parts of B1;
- B1(a) – offices
- B1(b) – research and development of products and processes
- B1(c ) – industrial process
- D1 – non residential institutions
- D2 – assembly and leisure
The changes include the amendment of the following Use Class;
- B2 (industry)
The changes include the introduction of the following Use Classes;
- E – commercial, business and service
- F.1 – learning and non-residential institutions
- F.2 – Local community
There are no changes to the following Use Classes;
- C1 – hotels, boarding and guest houses
- C2 – residential institutions
- C3 – dwellinghouses
- C4 – small HMO
From 1 September 2020;
- Small retail shops (not more than 280 sq metres net sales area) selling essential goods including food and at least 1 kilometre from another shop will cease being an A1 use and will become a F.2 (local community) use;
- Other A1 shops will become an E (commercial, business and service) use;
- A2 uses will become an E (commercial, business and service) use;
- A3 uses will become an E (commercial, business and service) use;
- A4 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
- A5 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
- B1 uses (included B1(a), B1 (b) and B1 (c) will become an E (commercial, business and service) use;
- B2 uses will either be B2 uses or will be Class E uses.
- Clinics, health centres, creches, day nurseries and day centres (previously D1 uses) will become an E (commercial, business and service) use;
- Schools, non residential education and training centres, museums, public libraries, public halls, exhibition halls, places of worship, law courts (previously D1 uses) will become an F.1 ( learning and non-residential institutions) use;
- Cinemas, concert halls, live music performance venues, bingo halls and dance halls (previously D2 uses) and will be sui generis, ie not in any use class;
- Gyms, indoor sport, recreation or fitness not involving motorised vehicles or firearms principally to visiting members of the public (previously D2 uses) will become an E (commercial, business and service) use;
- Hall or meeting place for the principal use of the local community (previously D2 uses) will become an F.2 (local community) use;
- Indoor or outdoor swimming baths, skating rinks, outdoor sports or recreation grounds (not involving motorised vehicles or firearms) (previously D2 uses) will become an F.2 (local community) use.
Changes of use within a Use Class do not constitute development. That being the case, provided the Order is applicable, its operation not having been restricted by planning condition, Agreement or Article 4 (1) Direction for example, planning permission would not be required, development as defined not happening. If legally binding confirmation is required that planning permission is not required this can only be obtained by way of a successful application for a Certificate of Lawfulness. In the absence of such, there is some risk.
It remains the case that planning permission may be required for operational works to buildings. It also remains the case that other consents and permissions may be necessary for example licenses. Furthermore amendments to leases may be required if the property is rented.
The Regulations additionally include transitional arrangements because of permitted development rights for changes of use in the Town and Country Planning (General Permitted Development) (England) Order amongst others. To respond to this Regulations introduce a ‘material period’ which is defined as meaning the period beginning 1 September 2020 and ending 31 July 2021. It is expected during the material period the Orders giving permitted development rights for changes for use which do constitute development will be amended / updated to reflect the new use classes.
Click here to view the Regulations.
The above is based on our understanding of the new Regulations at the time of issue and in advance of planning practice guidance being issued.
There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.
Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.
A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.
ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”
Employers will be collecting and sharing health information. Health information is sensitive and higher data protection standards apply. Here are a few key pointers.
- Update privacy notices to cover the new collection and sharing of employees’ information and provide these to the workforce. Be transparent and fair.
- Identify the legal basis and condition for use of this information and put any required paperwork in place. The ICO guidance will help. For some conditions such as the employment condition, an Appropriate Policy Document (APD) will be required. The ICO has an APD template.
- Only use the information for the purpose of managing the workforce during the pandemic.
- Only collect or share information if it’s necessary – if it’s a targeted and proportionate way of achieving your purpose.
- Make sure any health information collected and shared is accurate – there may be serious consequences if it’s not.
- Work out how long the information must be kept for. Keep a record of that period and act on it at the appropriate time.
- Security is very important – there may be malicious actors trying to trick employers and employees. Make sure employees know how to identify a genuine NHS Test and Trace contact. Keep the information secure. Use the ICO’s data sharing checklists** and keep a record of the disclosures made and why. Control external disclosures – only certain authorised members of staff should make them.
- Make sure individuals can still exercise their data protection rights – that’s also very important. Keep data protection records up-to-date and ensure any exports of personal information outside the UK are compliant.
- Before introducing employer-led testing like taking temperatures, thermal imaging or other potentially intrusive tests, work out if a data protection impact assessment (DPIA) is required. It will be if the intended processing is ‘high risk’. If it is, then carry out a full DPIA. It will help address the issues systematically and mitigate risks.
- All this demonstrates ‘accountability’ – it shows affected individuals and the ICO that the employer is complying with data protection requirements.
If you need further help, please visit the ICO’s data protection and coronavirus information hub or ask our data protection team.
** Please note that this link is to the ICO’s existing checklists and data sharing code of practice. We will update the link to the ICO’s new checklists after they are published.
Yes.
Workers (and agency workers) who are aware of the requirement to self-isolate and are due to work during their isolation period at a place other than their designated place (see below) must, as soon as reasonably practicable and in any event before they are next due to start work within the isolation period, tell their employer that they are self-isolating, and set out the start and end dates of their isolation period.
Clear communication to all workers about their obligation to do this is strongly recommended.