Skip to content

What will be the impact of the proposals on suppliers?

The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency.  This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.

In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted.  For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic.  These could include:

  • Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
  • Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.

This is potentially a very significant development for many businesses.  We would strongly recommend specialist advice be obtained so that:

  • businesses understand the potential increased risks faced; and
  • where possible, contracts are updated so that appropriate protections are maintained.

Related FAQs

What was the purpose of the Chancellor's economic update?

On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.

Is the Land Registry functioning?

Yes. The Land Registry published a new service update on 14 May, here:

https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service

Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

To summarise some further points:

  • Most information enquiries are experiencing minimal delays
  • Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
  • Cancellation dates for replying to requisitions are extended until further notice
  • Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
  • Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
  • Requests for extensions to a notice or objection period will be granted if lawfully possible
  • Land charges searches can be submitted electronically with PDF documents
What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Introduction to alternatives to redundancy

We hope that all organisations will come out of lockdown successfully. However, the current economic crisis means that many organisations will face very difficult trading conditions.

Employment costs are one of, if not the, largest cost to your organisation. These costs will have an effect on your financial well-being – and many organisations are now considering how to reduce employment costs. That said, your workforce is also your most important asset and as we get back to business, you will need your workforce to run the organisation, produce your goods, deliver your services and deal with your customers.

As a result, many organisations are facing a very difficult situation – how to reduce or flex the cost of the workforce whilst also maintaining an ability to service customers. This difficulty is enhanced by the uncertainty of when the pandemic will be controlled and the threat of lockdowns end.

Reductions in salary

An obvious cost cutting measure is to reduce salaries, either temporarily or permanently. If you are to seek a reduction in salaries, this should be done fairly – either across the board or by selecting teams/individuals based on objective business reasons.

Note that this cannot be imposed without significant risk. Without agreement, this would need fair selection and consultation.