Which charities will benefit from this funding and when – local charities?
£370 million will be available to support small and medium-sized charities who are at the heart of local communities and which are making a big difference during the outbreak, including those delivering food, essential medicines and providing financial advice. These monies will be distributed by organisations including the National Lottery Community Fund for those in England. It is understood these monies will need to be applied for. The application system for the National Lottery Community Fund grant pot is expected to be operational within a period of weeks.
Related FAQs
If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:
- The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
- The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
- The contractor should have sufficient control over how, when and where (if possible) they provide the services;
- A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task
We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
On 30th April 2020, the CMA issued a guidance note setting out its views about how the law operates in relation to refunds.
Where a contract is not performed as agreed, the CMA considers that in most cases, consumer protection law will generally allow consumers to obtain a refund.
This includes the following situations:
- Where a business has cancelled a contract without providing any of the promised goods or services
- Where no service is provided by a business, for example because this is prevented by Government public health measures
- A consumer cancels, or is prevented from receiving any services, because Government public health measures mean they are not allowed to use the services.
In the CMA’s view, this will usually apply even where the consumer has paid what the business says is a non-refundable deposit or advance payment.
This positon reflects the CMA’s previous guidance which they had issued in relation to the requirement of fairness in consumer contracts under the Consumer Rights Act 2015, which was that a clause in a contract that gives a blanket entitlement to a trader to cancel a contract and retain deposits paid is likely to be unfair, and therefore unenforceable – it would be unfair to a consumer to lose their deposit if the contract is terminated without any fault on their part, and if they had received no benefit for the payments made.
The CMA’s latest guidance therefore confirms their view that the Covid-19 outbreak does not change the basic rights of the consumer, and that they should not have to pay for goods or services that they do not receive.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Yes, however holiday pay during furlough must remain at the normal rate of pay and not the reduced furloughed rate. You can still claim for this period under the scheme but you will be responsible for any amounts beyond the maximum you can claim. Employers have flexibility to restrict when leave can be taken both during and after period of furlough in the normal way.
If an employee usually works bank holidays then the employer can agree that this is included in the grant payment. If the employee usually takes the bank holiday as leave then you would either have to top up their usual holiday pay, or give the employee a day of holiday in lieu.