Who pays?
If a dispute goes to court then the losing party will have to pay both their own and the winning parties’ legal costs. In other words, if you did not succeed with your claim, you would have to pay the legal costs incurred by the beneficiaries of the estate. However, if your claim succeeds, the beneficiaries of the estate are likely to have to pay your legal costs, as well as any financial provision which is ordered by the court to come from the estate.
Ward Hadaway can offer a number of options to help to minimise your financial outlay, including acting on a fixed fee basis or a no win no fee arrangement.
We have been offering no win no fee arrangements now for over 20 years. We know that good legal advice is expensive and in most cases, if the case is strong, we can work with you to find a way of bringing the claim. Costs will be discussed with you in detail before you have to pay anything.
Related FAQs
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
It is not unheard of for potential beneficiaries to produce a fraudulent or forged document which they say was prepared and signed by the testator. In these circumstances, detailed investigations need to be undertaken in order to establish the authenticity of the document which is produced, particularly if there was apparently no other parties involved in its preparation apart from the testator and the person who would benefit under the Will.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:
- Varying deadlines (e.g. for performance or payment)
- Varying compensation (e.g. to recognise increased costs)
- Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)
The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.
As above, employees must not leave their home unless they have a ‘reasonable excuse’.