Skip to content

Will I have to go to court?

The vast majority of disputes settle without ever reaching a final hearing with something in the region of 2-5% of all cases actually ending up in court at a final trial.  So whilst it is very unlikely you would need to attend a court hearing, it is always a possibility.

Related FAQs

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
What if the contractor is supplied by an agency?

As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.

If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.

If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.

What should businesses do now?

Many will have worked collaboratively with their suppliers and customers to deal with the immediate public health crisis. This will have meant offering flexibility as to contractual arrangements, whether in delivery dates, volumes of goods or services supplied, or even in the specification of what has been delivered.

If this is the case, it is important that businesses now do their legal housekeeping and make sure they have a proper record of what has been agreed. Unfortunately, our experience shows that many legal disputes arise out of amendments to contracts, typically where the parties to the contract each have a different view about what exactly they agreed to change.

We would therefore advise businesses to review any amendments that they might have agreed either verbally, by email, or otherwise, and consider whether they need to be captured in a more formal way which will make clear exactly what has been agreed to be varied, and (where appropriate) how long that variation will remain in force.

It’s also important to remember that some contracts contain provisions that set out specific requirements about how amendments are to be made. For example, they might require that amendments are made in writing (rather than verbally). These “No Oral Modification” clauses are commonly found in commercial contracts, and the courts have recently shown that they are willing to enforce them.

Failing to deal with amendments in accordance with contractual requirements could therefore have a serious impact on businesses as they recover from the disruption caused by the lockdown. If they end up in dispute with a customer or supplier, a business could find that the contract has not actually been amended in the way that they think – potentially leading to legal costs and liabilities at the worst possible time.