Skip to content

Will I need to make an application to the court for a remote hearing?

Despite remote hearings being the default position at present, formal permission will still be required by the court and a template order was circulated with the guidance. This template sets out the relevant directions and recitals to include in your order. An application to the COP for a remote hearing will not be required.

Related FAQs

What are the changes to the law?

On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process.  This has very important consequences for many businesses as it could expose them to greater financial risks.

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
Can charities furlough their employees?

Hopefully, further guidance will provide additional clarification on this, but it is difficult to see how a charity whose operations have been significantly curtailed because of the Covid-19 restrictions, cannot furlough employees and access the scheme, in particular where they have several different income streams. For example if a charity’s retail or fundraising operations have been significantly curtailed due to the restrictions, then it would appear unfair for it not to able to rely on the furlough scheme to assist in the funding of the employment costs associated with this part of the charity.

However, it might be prudent, where there are services that are publicly funded and employees working within those services cannot undertake their normal work, to consider if they can do different roles to work on Covid-19 activities. If there is no such work available then the guidance does appear to allow the furloughing of employees and such organisations to access the scheme.

In our experience, the funding streams and work undertaken by the organisations that could fall into the third category identified above can be exceptionally diverse and we would strongly recommend that you take advice before making such decisions about furloughing employees.

When does IR35 generally apply?

It would apply if the contractor uses an intermediary to provide their services or labour and they would be deemed to be an employee or office holder for tax purposes if they were hired directly by the end user client rather than via the intermediary PSC. This would of course require an assessment of employment status for tax purposes.

Contractors who are not taxed in the UK and supply their services exclusively from outside of the UK are unaffected.

If IR35 applies, tax and NIC’s should be deducted under PAYE by the PSC. In reality this has not been happening so a major reform of the regime was due to be implemented in April 2020. The changes were postponed by one year and are due to take effect from 6 April 2021.

“Within IR35” means a contractor arrangement is caught by IR35 and the individual should be taxed as an employee.

“Outside IR35” means a contractor arrangement is not caught by IR35 and the contractor status is fine.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?